What does a metal building cost in San Antonio?
No metal building company serving the San Antonio area posts a price, so nothing on this sheet is a San Antonio building price. A figure has to come as a quote on your own lot, because the frame gets engineered to your lot, span and use before anyone can quote it.
What this sheet carries instead: the things that move the number, and the fees the state, the city, the seven counties and the utilities post for themselves, each with where and when it was checked.
Lot picked out? Each request goes to one independent contractor, whose call it is which jobs to accept.
Can a metal building be priced before anyone sees the lot?
Nobody around here posts that answer. No metal building company serving the San Antonio area posts a price; the four company sites checked on 2026-09-13 all send you to a quote request.
So this site prints no range. A range lifted from a content guide is a number no one stands behind, and no metal building company serving the San Antonio area posts a figure for a completed one.
What you can pin down now is the paperwork that rides along. The agencies post those fees themselves, and on a small building they are a real slice of the budget. The order the job runs in: the start-to-finish San Antonio guide.
Company price pages checked; none shows a figure. Checked at Four San Antonio-area metal building company websites, 2026-09-13.
Why no San Antonio builder posts a price
A pre-engineered building is priced off a set of drawings, not a catalog page. The steel gets detailed for one span, one eave height, one wind load and one set of openings, then punched and welded for them before it leaves the plant. Two buildings with the same floor area can ride on two different frames.
State law writes part of this down. Occupations Code 1001.056 lets a building skip the state engineering chapter when nobody holds out to offer engineering services to the public and the building is one story, 5,000 square feet of floor or less, with no clear span wider than 24 feet across its narrow side; where a building that size has an unsupported span over 24 feet, the roof framing (trusses, beams and other members holding up the roof) still has to be engineered or pre-engineered. Clear span drives the frame, so the point where a building stops being a simple shed is a design line first and a price line second.
Checked at Texas Legislature Online, Occupations Code Chapter 1001, engineers and engineering, 2026-09-13.
What moves the number
Each of these changes the price of the same building. Get every one spelled out in the written estimate.
Size, and above all clear span. A wider bay with no columns needs a heavier frame, and past a 24-foot clear span the roof framing has to be engineered or pre-engineered.
Eave height, which drives the frame, the panels, the doors and the crane hours.
The design loads on the drawings, set by whatever code the local office has adopted.
Doors and openings, detailed into the steel before it ships, so moving one later means changing the frame.
Insulation and heating and cooling. A conditioned building is a different spec from open storage, and the state energy code reaches commercial construction.
Slab and soil. The foundation is engineered to the building and to the ground under it, and the soil report tells the engineer which ground that is.
Site work: clearing, cut and fill, compaction, drainage and the drive, each its own scope, and on a raw lot none of them small.
Finish-out. A shell is not an office, a restroom, or a shop wired for three-phase power.
Checked at Texas Legislature Online, Occupations Code Chapter 1001, engineers and engineering, 2026-09-13.
Checked at Texas Comptroller of Public Accounts, State Energy Conservation Office, commercial construction energy code, 2026-09-13.
State fees on a metal building job
Two state agencies, TDLR and TCEQ, post fees that can land on the job, and the registered accessibility specialist bills on top:
| Agency and item | Posted fee |
|---|---|
| TDLR project filing | $175, non-refundable |
| TDLR late project filing, when registered after construction is complete | $300, non-refundable |
| TDLR special review or inspection | $215 per hour, minimum one hour, non-refundable |
| TDLR variance application | $175 each, non-refundable |
| TDLR plan review and inspection | Set by estimated construction cost; no dollar tiers posted |
| Registered accessibility specialist | Set by the specialist; TDLR posts no amount |
| TCEQ Edwards Aquifer application, lots on a regulated zone | $650 floor, $10,000 ceiling; non-residential from $3,000 below one acre up to $10,000 at 100 acres and up |
| TCEQ stormwater Notice of Intent, on five-plus disturbed acres | $225 online, $325 on paper |
Checked at Texas Department of Licensing and Regulation, Architectural Barriers fee schedule, 2026-09-13.
Checked at Texas Department of Licensing and Regulation, Architectural Barriers special project registration application, 2026-09-13.
Checked at Texas Commission on Environmental Quality, Edwards Aquifer application fee form TCEQ-0574, 2026-09-13.
Checked at Texas Commission on Environmental Quality, general permit TXR150000, fees, 2026-09-13.
Reading the state fee table
The aquifer fee follows the acreage of the whole property inside its legal boundaries and the kind of development, and TCEQ counts commercial, industrial, institutional, multi-family and school sites as non-residential; the bands in between are on the Edwards Aquifer sheet. From one acre to under five disturbed acres there is no Notice of Intent to file, so under that permit it pays nothing. When TDLR registration starts is on the TDLR sheet for jobs over $50,000.
Checked at Texas Commission on Environmental Quality, Edwards Aquifer application fee form TCEQ-0574, 2026-09-13.
Checked at Texas Commission on Environmental Quality, general permit TXR150000, fees, 2026-09-13.
City of San Antonio commercial permit fees
Inside city limits the permit goes by valuation. On the city fee schedule, a commercial building permit runs a flat $115.00 at $1,000 or less; $115.00 plus $8.40 per $1,000 over $1,000, up to $25,000; $316.20 plus $6.60 per $1,000 over $25,000, up to $75,000; and $644.00 plus $2.30 per $1,000 over $75,000. Commercial plan review is billed separately, from a flat $115.00 at $1,000 or less to a top band of $5,311.20 plus $0.60 per $1,000 over $5,000,000.
You do not set the valuation alone. The schedule says Development Services sets minimum values for the cost of commercial remodels and swimming pools from International Code Council published costs, with the Army Corps of Engineers modifier for San Antonio, fixed when the plans go in, and plan examiners may check it again in review.
Trees are their own line: $115.00 for a tree plan review, and a commercial tree permit at $201.25 plus a $25.00 tree canopy fee. Starting site work without one brings a penalty fee, $2,300 at the least. Which office has your address: metal building permits in San Antonio and Bexar County.
Checked at City of San Antonio Development Services, FY 2027 development fee schedule, 2026-10-03.
County fees across the seven
Past the city limits the answer changes at each county line, and three of the seven post no building permit fee because they post no building permit. Under Local Government Code 233.061, a county may adopt a fire code only if it has more than 250,000 people or borders a county that size, and section 233.063 caps the fee at what it costs to enforce the subchapter.
Four counties post a Fire Marshal schedule, and each charges a small job a flat fee with a valuation table above it:
| County and schedule date | Flat permit fee | Plans review | Other posted items |
|---|---|---|---|
| Bexar, dated January 1, 2024 | $400.00 under $6,250.00 of valuation | $100.00 minimum | $200.00 final inspection and certificate of occupancy; 4.5 percent technology surcharge |
| Guadalupe, effective February 1, 2026 | $200.00 plus a technology fee | $100.00 minimum | $125.00 final inspection; $500.00 site preparation and foundation permit |
| Wilson, revised November 30, 2025 | $200.00 | $100.00 minimum | Fire Marshal Office, 830-393-8503 on the fee schedule; the Fire Marshal page lists 830-259-5612 |
| Atascosa, effective May 2023 | $200.00 | $40.00 | None listed here |
Checked at Texas Legislature Online, Local Government Code Chapter 233, county regulation of housing and other structures, 2026-09-13.
Bexar valuation, and the three counties with no building permit fee
One Bexar wrinkle: its fee schedule estimates commercial construction at $200.00 a square foot for valuation, while the county Code Enforcement page gives a minimum cost of construction of $25.00 a square foot, so ask Code Enforcement which one applies.
Medina, Frio and Karnes post other permits instead. Medina County's one-page permit list has five items and a building permit is not among them; it does post a floodplain development permit at $45.00 and septic at $200.00 conventional and $400.00 aerobic. Frio County posts septic at $200.00 residential and $450.00 commercial, and commercial right of way work at $500.00 per line or road crossing. Karnes County posts no septic, development or driveway fee on any page checked, so call the permits office. Wilson County also has a newer permit fee list, effective May 11, 2026, covering floodplain, septic and driveway fees, that does not render as readable text, so confirm current amounts with Permitting and Development at 830-393-8357. Checked at each county fee page, 2026-09-13.
No building permit fee does not mean no rules. Floodplain, septic and driveway permits, accessibility registration at $50,000, the aquifer plan where the zone reaches, and the stormwater filing by acreage all still apply, and inside a city, that city's rules do.
Checked at Texas Department of Licensing and Regulation, Architectural Barriers frequently asked questions, 2026-09-13.
Checked at Texas Commission on Environmental Quality, Edwards Aquifer Protection Program, 2026-09-13.
Checked at Texas Commission on Environmental Quality, construction stormwater general permit TXR150000, 2026-09-13.
What power, water and septic cost
The electric charge is figured job by job, and most of it is not posted. CPS Energy calls it the customer construction cost, or contribution in aid of construction: a one-time charge worked out per project from materials, labor and time on the job, under a line extension policy its board of trustees approved. No dollar amount, deposit or engineering fee for a new commercial hookup appears on any CPS Energy page checked. The co-ops post their up-front charges: Guadalupe Valley Electric Cooperative takes a $6,000 engineering deposit before design, and Medina Electric Cooperative a non-refundable $100 engineering fee before the site visit.
Water is the line that can surprise a commercial job inside the San Antonio Water System service area. SAWS charges a one-time impact fee on new development, quoted per equivalent dwelling unit, on a schedule in force from July 1, 2024. A one inch meter rates as two equivalent dwelling units, and its total water impact fee is $10,940.00 in the low elevation zone, $11,408.00 in middle elevation and $11,974.00 in high elevation. Sewer impact fees run $1,873.00 to $5,541.00 per unit, depending on area.
Septic is a county fee, and most of these counties post a separate commercial septic fee. Atascosa County charges $350 for a commercial conventional system and $600 for commercial aerobic, against $250 and $400 residential. Guadalupe County charges $600 for a commercial or multi-unit system, against $400 for residential conventional. Checked at the Atascosa County septic inspection fee schedule and the Guadalupe County Environmental Health fee schedule, 2026-09-13.
Checked at CPS Energy, customer construction cost, contribution in aid of construction, 2026-09-13.
Checked at Guadalupe Valley Electric Cooperative, developer and builder resources, 2026-09-13.
Checked at Medina Electric Cooperative, start or stop service, 2026-09-13.
Checked at San Antonio Water System, water and sewer impact fees by meter size, July 2024, 2026-09-13.
Getting a real price on your building
Send two things: the county the lot sits in, and what the building is for. The county sets which permit offices and fees come into it; the use sets whether accessibility registration, a city plan review or a commercial septic design come into it at all. The request is sent to one independent metal building contractor, whose call it is which jobs to accept.
Then get the estimate on paper, split by scope: building package, slab, site work and drive, utilities and septic, permits and reviews, finish-out. Ask which the contractor carries and which fall to you, and who files the accessibility registration at or over $50,000. A price that does not name its scopes cannot be held against another one.
Texas licenses no builder, so do not look to the price for a credential. Ask each bidder for the written estimate, an insurance certificate from the insurer, an engineered foundation plan, and the trade licenses for the electrical and mechanical work.
This sheet prints no financing terms and no loan figures. Which office takes a loan application for a building like this, from the SBA district office to the Farm Service Agency, is on the San Antonio metal building financing guide. Most jobs priced this way are a commercial steel building or a metal shop building, and the scope list is the same for both.
Checked at Sunset Advisory Commission, Texas Residential Construction Commission; TDLR regulated industries list, 2026-09-13.
Checked at Texas Department of Licensing and Regulation, Architectural Barriers frequently asked questions, 2026-09-13.
What owners ask
How much does a metal building cost in San Antonio?
No metal building company serving the San Antonio area posts a price, so no honest figure can be given here; the four company sites checked all send you to a quote request. A figure has to come as a quote on the actual lot, because the frame is engineered to one lot, one span and one set of openings before it is fabricated, and two buildings with the same floor area can ride on different frames. Checked at four San Antonio-area metal building company websites, 2026-09-13.
Which permit fees does a San Antonio metal building pay?
Inside city limits, the City of San Antonio fee schedule prices a commercial building permit on valuation: a flat $115.00 at $1,000 or less; $115.00 plus $8.40 per $1,000 over $1,000, up to $25,000; $316.20 plus $6.60 per $1,000 over $25,000, up to $75,000; and $644.00 plus $2.30 per $1,000 over $75,000. Commercial plan review is a separate fee starting at a flat $115.00, and Development Services sets minimum valuations. In unincorporated Bexar County, the Fire Marshal fee schedule dated January 1, 2024 charges a flat $400.00 building permit fee on a commercial or public access job valued under $6,250.00, with a valuation table above that. Checked at the City of San Antonio FY 2027 development fee schedule (2026-10-03) and the Bexar County Fire Marshal fee schedule, Appendix A (2026-09-13).
What does TDLR registration add to a metal building budget?
Fees, once the total estimated construction cost reaches $50,000. TDLR posts a filing fee of $175 per project, $300 for late filing, special review or inspection at $215 per hour (minimum one hour), and $175 per variance application, none refundable and all due before the service. Two costs carry no posted number: the plan review and inspection fees TDLR collects go by the estimated cost of construction, and no dollar tiers are posted, and the registered accessibility specialist who does the plan review and inspection sets a separate fee TDLR prints no amount for. Checked at the TDLR Architectural Barriers fee schedule and the special project registration application, 2026-09-13.
Why is there no metal building price range on this site?
A figure prints here only when a builder, a manufacturer or an agency posted it, and no company serving the San Antonio area posts one; the four company sites checked all send you to a quote request. So this sheet prints what moves the number, plus the fees the state, the city, the counties and the utilities post for themselves, each with where and when it was checked. Checked at four San Antonio-area metal building company websites, 2026-09-13.